TL;DR: This cheat sheet defines 25+ construction acronyms used daily in GC preconstruction, estimating, and project delivery. From RFI and RFP to GMP, T&M, CCDC, and NTP, each entry gives you a plain-English definition and the context where it matters most. Bookmark it. Share it with your team.
Construction runs on shorthand. Walk into any preconstruction meeting and you'll hear RFIs, GMP, SOW, T&M, and NTP in the first five minutes. Everyone nods. Not everyone agrees on what they mean.
That gap is expensive. A $400K roof cover board ends up in nobody's scope because two estimators used "SOW" to mean different things. A sub prices T&M on a job the GC expected as a lump sum. Disputes like these average $60.1 million in North America, according to the 2024 Arcadis Global Construction Disputes Report. Shared language is the first line of defense.
This cheat sheet is built for GC preconstruction and estimating teams. It covers the acronyms that come up at bid, buyout, contract review, and project kickoff.
An RFP is an owner's formal invitation for GCs to submit a detailed proposal. It goes beyond price. It asks for methodology, team qualifications, schedule, and sometimes fee structure. RFPs are common on design-build, CM-at-risk, and negotiated projects.
An RFQ asks firms to demonstrate capability before they receive a full RFP. Owners use RFQs to shortlist. If you respond to an RFQ and make the short list, the RFP follows.
An IFB is a hard-bid invitation. Documents are fixed. Price is the primary selection criterion. Common on public work. No negotiation, no best-and-final: low compliant bid wins.
An ITB is what GCs send to subcontractors. It packages the scope of work, bid instructions, and the relevant drawings and specs for one trade. A well-written ITB tells the sub exactly what to price. A vague one guarantees inconsistent bids and expensive leveling sessions.
Provision's Scope Agent generates trade-specific ITBs directly from your digital project documents, so subs price what you mean rather than what they assume.
Similar to an RFQ response. A SOQ is the formal document a firm submits to demonstrate relevant experience, bonding capacity, and team credentials. Often the first gate on public-sector and institutional pursuits.
An EOI is a lightweight prequalification step. Owners post an EOI before drafting full procurement documents. Responding signals interest and sometimes unlocks access to the RFQ or RFP.
A GMP contract sets a ceiling on what the owner pays. The GC carries the risk if costs exceed the cap. Savings below the GMP are sometimes shared. GMP contracts require precise scope definition early. A scope gap in a GMP job is a loss the GC absorbs.
As a Pre-Construction Lead at a Top-ENR Canadian GC put it: "If you miss anything, they'll bill it." GMP makes that statement literal. Early scope definition narrows that risk down to the truly unforeseen, which you have contingency to cover.
T&M means the owner pays the actual cost of labor, equipment, and materials, plus a fee or markup. There is no fixed price. T&M is common on change orders and undefined-scope work. It shifts cost risk to the owner but requires rigorous tracking to avoid disputes.
In design-build, one entity contracts for both design and construction. The GC (or a GC-led team) is responsible for the finished product, not just the work described by someone else's drawings. Scope definition on DB work is especially critical because drawings are incomplete at procurement.
The traditional delivery model. The owner hires a designer first. Documents are completed. Then the owner bids the work to GCs. The GC builds to drawings it had no hand in creating. Most hard-bid public work is DBB.
The GC (acting as construction manager) joins the project during design. It provides preconstruction services, then takes on financial risk for delivery at a GMP or lump sum. Also called CMAR or CMR.
CCDC publishes standard contract forms used across Canadian construction. CCDC 2 is the stipulated price contract. CCDC 5A and 5B cover construction management. If you're a Canadian GC, you work inside CCDC documents constantly. Understanding the standard supplementary conditions matters as much as knowing the base form.
In a contract context, AIA refers to the standard contract documents the AIA publishes. A201 is the general conditions form used on most U.S. commercial work. When someone says "we're using an AIA contract," they mean an owner-issued document built on AIA forms, often with owner modifications.
CCA develops industry standards, model specifications, and best practices for Canadian contractors. CCA documents often appear alongside CCDC forms in Canadian project specifications.
The SOW is the written description of what a subcontractor is responsible for delivering. It is the most important document the GC produces at buyout. A vague SOW creates change orders. A precise SOW eliminates them.
The most cited anti-pattern in preconstruction is writing "as per plans and specs" and calling it a scope. That phrase assigns nothing. It guarantees disputes. See Chapter 5 of the Scope Gap Playbook for how the best-margin GCs write scope language that holds.
An RFI is a formal question from the GC or a sub to the design team, asking for clarification on drawings, specs, or contract documents. RFIs document the question and the response. They create a record if a dispute arises later.
Catching the conflicts that drive RFIs before tender is faster and cheaper than issuing them during construction. Provision's RFI Agent reviews drawings and specifications against each other, surfacing more than 100 potential issues from a document set in an hour.
An ASI is a direction from the architect that clarifies or supplements the contract documents without changing the contract price or time. If an ASI does change price or time, it should trigger a change order. Knowing the difference matters at claim time.
A PCO is a flag raised by the GC or a sub that work may be outside the original contract scope. It is not yet a change order. It is a notice. Teams that track PCOs rigorously have a paper trail. Teams that skip them often absorb the cost later.
A CO is an executed change to the contract: price, scope, or schedule, or any combination. Change orders that reflect genuine owner-directed changes are normal. Change orders that result from scope gaps in the original bid are profit erosion.
The NTP is the owner's written authorization for the GC to begin work. The contract start date and schedule often run from NTP. Never mobilize without one in writing.
An NOC is a legal notice filed by the owner at the start of a project, typically recorded with the local authority. It establishes the project's lien rights timeline. Requirements vary by state and province.
These are the three main design phases on a traditional project. SDs are early-stage sketches: enough to establish program and massing. DDs advance the design with more detail. CDs are the fully coordinated drawings and specs issued for permit and construction. Bidding off DDs instead of CDs is a common source of scope gaps on fast-track jobs.
BIM is the use of a 3D digital model to design, coordinate, and document a building. For GCs, BIM matters most at coordination: clash detection between mechanical, structural, and architectural elements before work is built in the field. BIM does not replace a well-written scope of work.
MEP refers to the three major building systems trades. MEP is where the most expensive scope gaps concentrate. Generator field conditioning, motor starters, lighting controls, and fire-rated louvres all routinely fall between MEP subcontract scopes. See Chapter 5 of the Scope Gap Playbook for a full breakdown of common MEP gaps.
An ITP is a document that defines what needs to be inspected, who inspects it, and what acceptance criteria apply. ITPs are common on ICI work and institutional projects. Missing ITPs in a scope is a testing-and-certification gap. Scope Agent flagged testing, inspection, and certification items in 47% of Division 01 packages reviewed in Q3 2026, across 20 projects, in the Scope Gap Index.
QA is the system: the processes that ensure quality is built in. QC is the inspection: checking that the work meets the standard. Both generate documentation. Both generate costs that need to be in someone's scope.
GC&P covers the GC's project overhead: superintendent, site trailer, temporary utilities, safety, insurance, and similar costs. These are not trade costs. They are the cost of running the project. Underpricing GC&P is a fast way to lose money on a fixed-fee job.
OH&P is the markup applied to direct costs. Overhead covers the GC's home office costs. Profit is the return for taking on project risk. On change orders, negotiating OH&P percentages is standard. Know your floor before bid day.
A BOQ is an itemized list of all materials, parts, and labor required to construct a project. More common in the UK and Commonwealth markets than in the U.S., but used on some Canadian institutional and public work. A BOQ gives every bidder the same quantity base, reducing ambiguity.
An LOI is a written commitment from an owner to award a contract, allowing the GC or a sub to begin mobilization before the full contract is executed. An LOI is not a contract. Understand what it does and does not authorize before spending money against it.
The danger is not the acronym itself. The danger is when two people use the same acronym to mean slightly different things and nobody checks.
An ITB that says "include all MEP work" tells every sub something different. One includes testing. One excludes it. One prices motor starters. One assumes they are in the electrical package. The scope leveling session catches some of it. The rest turns into change orders.
The 2018 PlanGrid and FMI study "Construction Disconnected" put the annual U.S. cost of rework from miscommunication and bad project data at $31.3 billion. Shared language inside preconstruction is the cheapest fix available.
If your team is spending hours reading through specs to verify what's in and what's out before an ITB goes out, Provision's Scope Agent can generate trade-specific scope packages directly from your digital project documents. Every scope item is source-traced to the exact page and section. No assumptions. No gentleman's agreements.
For contract language questions at bid or buyout, Chat Agent answers questions across drawings, specs, contracts, and addenda in under 20 seconds, with every answer linked to the exact source.
And for a deeper look at how scope gaps form and what the best-margin GCs do about them, the Scope Gap Playbook is built from 200+ GC interviews and covers every phase from bid to buyout.
An RFP (Request for Proposal) asks for a full proposal including price, methodology, and team. An RFQ (Request for Qualifications) asks only for credentials and experience. Owners use RFQs to shortlist firms before issuing a full RFP. You may need to respond to both on the same pursuit.
GMP stands for Guaranteed Maximum Price. It is a contract ceiling: the GC agrees the owner will pay no more than this amount. Costs above the GMP are the GC's risk. Scope gaps on a GMP project become direct losses, which makes early scope definition critical on CM-at-risk and design-build delivery.
A PCO (Potential Change Order) is a notice that work may fall outside the original contract scope. It is not yet approved or priced. A CO (Change Order) is an executed modification to the contract, agreed by all parties, that changes price, scope, or schedule. PCOs that go untracked often convert into disputes rather than approved COs.
SOW stands for Scope of Work. It is the written description of exactly what a subcontractor is responsible for delivering. A vague SOW creates change orders. The most common anti-pattern is writing "as per plans and specs," which assigns responsibility to nobody. Specific, trade-tailored SOWs are the foundation of clean buyout.
CCDC (Canadian Construction Documents Committee) publishes standard contract forms used in Canada. AIA (American Institute of Architects) publishes the equivalent forms widely used in the United States, with A201 as the most common general conditions document. Both are templates. Both get modified by owners. Know the base form before reviewing the supplementary conditions.
NTP stands for Notice to Proceed. It is the owner's written authorization for the GC to begin work. Contract schedules and milestone dates typically run from the NTP date. Mobilizing without a written NTP creates risk around schedule obligations and cost recovery if the project is delayed or cancelled before execution.
MEP stands for Mechanical, Electrical, and Plumbing. MEP scope gaps most often occur at the interfaces between trades: generator field conditioning, motor starters, lighting controls, and fire-rated louvres are common examples. These items appear in the drawings or specs but fall between subcontract scopes, and no trade prices them without being explicitly assigned.