Podcast · September 15, 2026 · 52 min

Civil Precon, Geotech Risk and AI Guardrails

Spencer Thompson of Cardinal Civil Contracting on what changes when you are estimating dirt

Also on Spotify and Apple Podcasts.

Site-development preconstruction does not work like vertical. Spencer Thompson of Cardinal Civil Contracting explains what changes when the thing you are estimating is dirt, why true production is the number that matters, and where he draws the line on AI inside the business.

Civil is not vertical, and the tooling shows it

Most construction technology is built with vertical work in mind, and civil contractors notice. Spencer is precise about the difference: earthwork and underground utilities need three-dimensional calculation, not three-dimensional visualization.

His team does not use BIM, because BIM is a vertical answer. They are CAD people. What they need is software that can process civil CAD files, which means tools like Agtek, Insite and TBC.

And his frustration is that regardless of which one you pick, the workflow has not changed in years. Import the CAD file, move the data over, work it. That has been the shape of the job for as long as he has been doing it, which is a telling observation about where civil has been underserved while vertical preconstruction attracted the attention.

How the work gets priced is a judgment call, repeatedly

Asked whether two contractors would look at the same site the same way, Spencer says yes and no. Everyone can ask the same questions, but another contractor might focus somewhere different, or see something his team does not.

The way you move dirt varies from contractor to contractor, and even from superintendent to superintendent. Cardinal holds many meetings on means and methods before a project starts, precisely because the approach is not determined by the documents.

What they look for does change based on what is actually going to be built on the site. Subdivision work and other job types pull the estimate in different directions. This is the part that resists automation most stubbornly: it is not measurement, it is a plan for how to execute, and reasonable experts disagree.

True production is the number nobody has

The thing Spencer wants most is not a better takeoff. It is true production: understanding what crews actually did, over time, rather than what someone reported they did.

He is generous about why this is hard, and honest that it is a human problem rather than a technology one. Every company he has worked at has tracked dirt, and tracked it differently. Drones. Load counts. A person with a ticker counting. Bucket counts multiplied out by the cubic yard capacity of the excavator. All of it is an attempt to reconstruct what happened, and all of it drifts from the truth.

This is a different problem from estimating accuracy, and arguably a more valuable one, because an estimate is only as good as the production rates underneath it.

Where he draws the line on AI

Spencer separates two things that often get discussed as one, and the distinction is useful for anyone selling into a contractor.

A software vendor handling your data is a procurement question with established answers. Meet SOC compliance and the conversation can proceed on normal terms.

What he means by AI security is different: an employee opening ChatGPT or Claude in a browser and pasting company material into it. Unleashing that across an entire company is the thing Cardinal is cautious about, and that caution is about guardrails rather than about the technology being useless.

He is not an AI sceptic. He gets more latitude than most people in the business because the IT team knows what he does and trusts him with it, and he has built tools that genuinely help the workflow. His favourite use so far is unglamorous and believable: searching across masses of documents, comparing against previous work, and replacing outdated programs inside an existing process.

He also has a wish, which says something about what civil preconstruction still lacks. He would like a LIDAR and GIS baseline across the United States, so a team could pull up what already exists on a site and start designing from it.

In their words

Quotes are lightly edited for clarity. Listen to the full episode for the full context.

“When I say three-dimensional, I mean three-dimensional calculation. Underground utilities and earthwork. We do not use BIM because that is vertical. We are CAD people.”

Spencer Thompson, Cardinal Civil Contracting

“All of these tools, regardless of where you go in the market, it is still import CAD file, move data over. It has been the same workflow for years.”

Spencer Thompson

“The way you move the dirt can vary from contractor to contractor, even from superintendent to superintendent. We have so many meetings talking about the best means and methods to run this project before we even start it.”

Spencer Thompson

“The biggest thing is true production. Understanding true production, not what somebody is telling you they did, but seeing what they did in time.”

Spencer Thompson

“There are a lot of different ways to track dirt. Drones, load counts, a guy with a ticker sitting there counting. How many buckets did you scoop out with this excavator, and then you understand the bucket size.”

Spencer Thompson

“For a software company, that would not be that big of a deal, you would just have to meet SOC compliance. When I talk about AI security I specifically mean someone getting on their computer and going into ChatGPT, just the website. If we unleash that to the entire company, what happens there?”

Spencer Thompson

“It is a great indexing tool, to search through masses of documents and compare against previous things.”

Spencer Thompson

Questions this episode answers

How is civil preconstruction different from vertical construction?

What you are estimating is dirt. Spencer Thompson describes earthwork and underground utilities as needing three-dimensional calculation rather than three-dimensional visualization, and the approach to moving that dirt varies by contractor and even by superintendent.

Why don't civil contractors use BIM?

Because BIM is a vertical answer. Cardinal are CAD people, and what they need is software that processes civil CAD files, which means tools like Agtek, Insite and TBC. Spencer's frustration is that the workflow across all of them has not changed in years: import the CAD file, move the data over.

How do contractors measure earthwork production?

Badly, and in many different ways. Drones, load counts, a person with a ticker, or bucket counts multiplied by excavator capacity. Spencer's point is that what he actually wants is true production, meaning what crews did over time, rather than what someone reported they did.

Is it safe to let employees use ChatGPT at a construction company?

Spencer separates two things. A software vendor handling your data is a procurement question with established answers, such as SOC compliance. What concerns him is an employee pasting company material into a chatbot in a browser, and that is about guardrails rather than the technology being useless.

Read next
The Scope Gap Playbook →

Spencer's point is that the risk sits in what the documents do not tell you. The playbook covers how scope gaps get found before they become change orders.