Clark Construction is an employee owned general contractor in the Puget Sound region of Washington. The team builds multi family housing, community buildings and commercial work.
Scoping took a week per project
One senior manager or estimator wrote every subcontractor scope from the drawings and specifications. On an $8 to 10 million project, that took about a week.
Only senior staff could write a scope
Writing a scope and checking it needed someone with 30 to 40 years of experience. The people who had it were needed on everything else too.
RFI answers took up to three weeks
Contracts now give the architect and owner up to three weeks to answer an RFI. On a six month project, a late question costs money.
On how the RFIs used to come out:
“It usually takes the life of the project to get all those questions out, and you usually don’t get them all out.”
— Rachele Turnbull, CEO, Clark Construction
On what surprised her:
“I didn’t expect it to be as intuitive as it is. It’s not just accurate. It’s also thinking big picture.”
— Rachele Turnbull, CEO, Clark Construction
On a recent public bid, RFI Agent came back with 397 conflicts. Rachele dropped the minor items and the duplicates and kept the 100 that would change the price for Clark or for another bidder. That took three hours. The questions went to the architect before the bid date.
On sending 100 questions before the bid:
“It really did affect the cost of the bid. It levelled the playing field at the beginning of the project instead of fighting these issues later.”
— Rachele Turnbull, CEO, Clark Construction

On what she would tell another general contractor:
“It’s not so much the hours. It’s being able to get the questions you didn’t know to ask out before the bid. That saves many more thousands of dollars than the hours you save.”
— Rachele Turnbull, CEO, Clark Construction